College Heights & Quivera Storm Sewer Project

Project Description


Collapsed storm sewer under College Heights Road will be replaced, and storm inlets will be added on Quivera Circle to improve drainage in the area. Josh Connet Excavation will be the contractor on this project.

Budget


  • Total construction costs of $229,784.58 will be paid from the Stormwater Fund

Timeline


Award of bid May 16
Construction timeline May-August

Related Projects


None