Details
This annual maintenance project will rehabilitate pumps on Low Service Pump Station Pump No. 3 and Pump No. 5. This will include mobilization, pulling existing pumps, inspection with report, repair and/or replacement of pump shafts, pump discharge head, clean stuffing box port, installation of new bronze bushing and new packing, reinstallation, commissioning and demobilization. The motors on these pumps are new and will not be included in the scope of work.
Timeline
All work to be completed by May 31, 2019
Budget
$50,000
Project Number
WA1903